Extension projects
| |
Extension step one (summer 2006) |
|
| |
- Dismounting of single chair lift inclusive stations
- Constructing of a detachable quad chair lift
- Spreading of the downhill run from five to fifteen metres
- Transferation of the bottom station 300 metres upwards
- Contruction of a utility building with cash desk and sanitary facilities for guests
- Extension of the already existing parking site
- Extension of the snow blower system downwards to the bottom-station
- Setting up of another storage pond with a water capacity of 11.000 cubicmetres.
Construction period: mid-April till the end of September 2006. Since winter season 2006/2007 our guests have access to the newly constructed quad chair lift “Sonnenbahn”.
Start-up of the scooter course service was at the beginning of summer season 2007.
|

A: New quad chair lift, detachable
B: Spreading of the downhill run to 15 metres |
| |
| Project costs exstension step 1 (in millions of Euro) |
| Quad chair lift, detachable type |
€ 2,9 million |
| Extension downhill run inclusive storage pond |
€ 0,5 million |
| Snow blower system |
€ 0,3 million |
| Utility building |
€ 0,7 million |
| Clearing, transfer fee, parking site, diverse expense |
€ 0,1 million |
Total expense |
€ 4,5 million |
|

Utility building Mönichkirchen.

|
| |
Exension step 2 (summer 2006) |
|
| |
- Dismounting of Wechsellift I and Wechsellift II
- Constructing of a detachable quad chair lift
- Contruction of a utility building with cash desk and sanitary facilities for guests
- Construction of a garage for 2 crawler type vehicles
- Extension of the already existing parking site
- Setting up a crossover bridge close to Gasthaus Fernblick
Construction period: May till October 2006, start-up of the new quad chair lift named “Panoramabahn” was carried out at the beginning of winter season 2006/2007.
|

New quad chair lift, detachable
|
| |
| Project costs exstension step 2 (in million of Euro) |
| Quad chair lift, detachable type |
€ 3,5 million |
| Utility building, cash desk, sanitary facilities |
€ 0,2 million |
| Garages, Clearings |
€ 0,1 million |
Total expense |
€ 3,8 million |
|

Modern detachable chair lifts ensure comfortable access and high speed transportation for the passengers. So the duration of transport is shortened considerably. |
| |
Extension step 3 (summer 2007) |
|
| |
- Dismounting of B-Lift
- Transferation of the bottom station 200 metres downwards
- Transferation of the exit station 50 metres rightwards
- Construction of a solidly clamped quad chair lift
|

A new quad chair lift is going to replace the B-lift at the beginning of winterseason 2007. Because of the shorter distance solid mounted chairs will be in use.
|
| |
| Project costs Extension step 3 (in million of Euro) |
| Construction of quad chair lift solidly clamped |
€ 1,7 million |
Total expense |
€ 1,7 million |
|

Snow guarantee during the whole winter |
|